Applied assessment — Flow and capacity
A line feeds 70 pieces/hour to an operation producing 50. Calculate the queue after three hours and propose a controlled balancing trial.
Module quiz
5 questions on Module 2 — Sewing Flow. Answer them all, then check your score before moving on. 4 correct or more is a pass. Your best score is saved on this device, and to your account when you are signed in. This is a self-check, not an accredited assessment.
1. A line feeds 70 pieces/hour to an operation producing 50. What is the defensible first decision?
2. For this case, what makes the release decision auditable?
3. After correcting this issue, when is the action ready to close?
4. Which boundary matters when using this illustrative case on a real order?
5. What should the next shift receive after this incident?