Applied assessment — time study, SMV and the operation bulletin
Build and defend a standard minute value, and turn it into an operation bulletin a line can run.
Module quiz
8 questions on Module 1 — Work Measurement. Answer them all, then check your score before moving on. 6 correct or more is a pass. Your best score is saved on this device, and to your account when you are signed in. This is a self-check, not an accredited assessment.
1. Observed time is 0.80 minutes and the operator is rated at 110 per cent. What is the basic time?
2. Basic time is 0.88 minutes and total allowances are 15 per cent. What is the standard minute value?
3. What does a relaxation allowance cover?
4. Why is a single observed cycle an unsafe basis for an SMV?
5. Total work content is 22.5 standard minutes and you plan 60 pieces an hour on the line. How many operators does the takt require at 100 per cent efficiency?
6. What must the operation bulletin state that a simple operation list does not?
7. An IE presents an SMV rounded down so the costing looks competitive. What is the consequence?
8. Method study comes before time study because: