Sampling plan practice

Work the accept or reject decision on eight lots, using the plan figures each scenario gives you.

Who this is for: Final inspectors, QA officers, and merchandisers who sign off inspection reports.

How to use it: Each scenario states the lot size, the plan the buyer's programme applies, and the accept and reject numbers from that plan. Your job is the decision and the reasoning, not the table lookup. Take the drill again until the decision comes automatically.

The scenarios and figures here are written for this drill. No published sampling table or standard is reproduced: where a plan figure is needed, the scenario states it. Always work to your own buyer's programme and the current standard in production.

Read these first

Module quiz

8 questions on Sampling plan practice. Answer them all, then check your score before moving on. 6 correct or more is a pass. Your best score is saved on this device, and to your account when you are signed in. This is a self-check, not an accredited assessment.

  1. 1. Lot 3,200 pieces. The plan gives a sample of 200 with accept 10 and reject 11 for major defects. You find 9 major and 14 minor. What is the decision?

  2. 2. Same lot and plan. You find 11 major defects, and two of them are the same fault on the same operation. What is the decision?

  3. 3. Lot 800 pieces, sample 80, accept 5 reject 6 for majors. You find 5 majors and one broken needle fragment inside a garment. What is the decision?

  4. 4. Lot 12,000 pieces presented in three colours. The buyer's plan treats the lot as one. Which sampling approach is right?

  5. 5. The factory offers you 200 pieces they have already selected for inspection. What do you do?

  6. 6. Lot 5,000 pieces, sample 200, accept 7 reject 8 for majors. You find 7 majors, and measurements on 6 pieces are outside tolerance. The programme treats measurement failure as major. What is the decision?

  7. 7. A lot fails. The factory sorts 100 per cent, removes the defects and presents it again. How should the re-inspection be handled?

  8. 8. Your report says 'accepted with comments' for a lot that exceeded the reject number. Why is that phrase dangerous?