Module 8 assessment
Production Planning & Industrial Engineering
5 questions. 75% passes the module, and you can retry as often as you like. Every answer is explained, so a wrong answer still teaches you something. This is self-study practice written by NOSK.life, not an examination.
Checking your account…
- Question 1Multiple choice
SMV stands for and means
- Question 2Multiple choice
Line balancing aims to
- Question 3True or false
If the bottleneck station produces 300 pieces an hour, the line can still output 380 by speeding up the other stations.
- Question 4Multiple choice
A time study is invalid if
- Question 5Factory scenario
Total garment SMV is 20 minutes, the line has 40 operators and works 8 hours. What is a realistic daily target at 60 per cent efficiency?
Practical exercise
Take any five-operation sequence, assign your own SMVs and balance it for 30 operators. State your bottleneck and target.
Factory case study
A line hits target on day four but loses 30 per cent on day one. List the causes you would test and the data you would collect.