Module 6 assessment
Material Sourcing & Supply Chain
5 questions. 80% passes the module, and you can retry as often as you like. Every answer is explained, so a wrong answer still teaches you something. This is self-study practice written by Sanjeewa Dehiwalage, not an examination.
- Question 1Multiple choice
Supplier governance mainly exists to
- Question 2Multiple choice
Nomination of a fabric mill by the buyer means the factory
- Question 3True or false
A material in-house date earlier than the production start date is padding that should always be removed.
- Question 4Multiple choice
Which document proves what was actually agreed on a trim order?
- Question 5Factory scenario
Two trim suppliers quote the same price, but one has a history of late partial deliveries. What decides?
Practical exercise
Write a five-line incoming material acceptance rule for one trim: what you check, how many, against what, and what happens on failure.
Factory case study
A nominated mill ships 6 per cent short. Plan the recovery: cutting, consumption, buyer conversation and the record you keep.