← Module 7: Time Management Part 2

Activity 6 of 11

Factory case

Bangla is being improved for factory-floor accuracy and native wording. It will return once the review is complete. English is available now.

Listen to this article
Ready
100% Free

This lesson and the entire academy are free of charge — no fees, ever.

A senior manager loaded three lines at 95% based on a style SMV of 18.2, but the real average over the first week was 20.4 because the back pocket operation was slower than standard.

The line hit its hourly target until hour six, then fell behind every hour. A 30-minute buffer before final inspection would have caught the backlog, but instead 1,800 pcs shipped air to recover two days.