Skip to content
Skip to content
GARMENT Ed
Public reference reading

You are reading this page as a free public reference resource. Sign in with a free learner account to follow the structured course, where each step unlocks only after the previous one is passed.

Sign in to follow the course
← Module 14: Planning and Agility

Activity 8 of 11

Exercise

Bangla is being improved for factory-floor accuracy and native wording. It will return once the review is complete. English is available now.

Listen to this article
Ready
100% Free

This lesson and the entire academy are free of charge — no fees, ever.

You are managing five lines of chino trousers due to ship in twelve days. The main fabric arrives four days late because of a vessel delay. Replan the order using the following steps.

First, list the operations that can start before the fabric arrives and those that cannot. Second, identify the new critical path and the earliest possible ex-factory date. Third, calculate the cost of a two-day delay against the cost of partial airfreight for 20% of the order. Fourth, write the decision you would present to the buyer with owners and deadlines.