Skip to content
Skip to content
GARMENT Ed
Public reference reading

You are reading this page as a free public reference resource. Sign in with a free learner account to follow the structured course, where each step unlocks only after the previous one is passed.

Sign in to follow the course
← Module 2: Introduction

Activity 6 of 11

Factory case

Bangla is being improved for factory-floor accuracy and native wording. It will return once the review is complete. English is available now.

Listen to this article
Ready
100% Free

This lesson and the entire academy are free of charge — no fees, ever.

A factory accepted a 60,000 pcs knit polo order with a 45-day lead time. Costing assumed 12 lines at 78% efficiency, but PP approval arrived five days late because the buyer's trim colour was unconfirmed.

Planning kept the original ship date, production started with substitute trims, and 4,200 pcs were reworked. The order shipped on time but the CM margin fell by 9% — a hand-off problem, not a sewing problem.